Service contract for the drafting of the project of conditioning, installation and commissioning of estaciones regables
On July 23, 2019, Land, Water, and Dams was commissioned the SERVICE CONTRACT FOR THE DRAFTING OF THE PROJECT OF CONDITIONING, INSTALLATION AND COMMISSIONING OF ESTACIONES REGABLES R001 (DRAINAGE OF THE CANAL ALTO DEL BIERZO), R002 (INTAKE OF THE CANAL BAJO DEL BIERZO), R003 (DRAINAGE OF THE CANAL ALTO DEL BIERZO) BIERZO) AND R004 (TAKES THE ALTO VALLE DE LEMOS CHANNEL) IN LEÓN AND LUGO.
The work began by collecting field data in each of the control points studied in the project. Next, it focused on the preparation of the basic information necessary for the execution of the work. Finally, it calculated the full expenses needed to complete the project.

The conditioning, installation, and commissioning of the LAS ESTACIONES REGABLES, included the drafting of the conditions needed for the execution of the works. These are described below:
- In the DESAGÜE CANAL ALTO DEL BIERZO (R001): (1) Supply and installation of a piezoresistive sensor, and of (2) new solar panels. (3) Reconditioning of the Control Cabinet, and (4) replacement of the weir plate.
- In the TOMA DEL CANAL BAJO DEL BIERZO (R002): (1) Supply and installation of new piezoresistive sensors and of (2) new solar panels. (3) Reinstallation of the Radio-modem Antenna, (4) reconditioning of the Control Cabinet, and (5) installation of a handrail
- In the case of the DESAGÜE DEL CANAL BAJO DEL BIERZO (R003): (1) Supply and installation of the piezoresistive sensor and (2) reconditioning of the Control Cabinet.
- At the TOMA DEL CANAL ALTO DEL VALLE DE LEMOS (R004): (1) Supply and installation of a new doppler sensor, (2) reconditioning of the Control Cabinet, and (3) installation of a handrail.
The draft of the project included the establishment of the work plan, the creation of a detailed plan of the facilities, and the determination of the necessary budgets for its execution.
After successive reviews, the project was finally delivered in November 2019.